May 19, 2024
25MVA High Voltage Power Station Project in Atakupame,Togo
Time: 2024.05
Location: Atakpamé, Togo
Supply Voltage: 20kV
Total Capacity: 25MVA
The project is located in the Atakpamé region of Togo, close to the main highway, which is convenient for grid connection and maintenance. The supply voltage is 20kV, the total capacity is 10MVA, and the 20kV transmission line of about 15 kilometers uses aluminum core conductors (ACSR). It took 2.4 years from preliminary planning to commissioning. It provides power to agricultural processing enterprises and surrounding communities in the central region of Togo, while supporting the load balancing of the national grid.